3 week look ahead 8/26

Week of 8/26/24- Conneely completes North precast concrete retaining wall, start NW/garage precast retaining wall, cultec system on site .
Pittol Concrete start prepping SOD w/ chairs,wire &re-bar - complete ready to inspect 8/27/24 ,waiting for thermal break tapered insulation and shoring from white cap , then install prior to pour. UTS & building inspector scheduled to inspect Wednesday 8/28/24 noon .
WhiteCap - to deliver taper insulation/ thermal break & SOD Shoring
Week of 9/2/24 - Conneely - continue precast wall on west side, cultect system, infrastructure, dig underground garage floor drains, plumber to install cast iron
Pittol - pour slab SOD - 250 yards +/-
Week of 9/9/24  Conneely continue prepping site. Hayes engineering - establish control on SOD for Turnkey
Turnkey to conduct layout post set control by Hayes
Week of 9/16/24 ready for turnkey to start framing