3 week look ahead 6/10

6/10/24 :

Hayes Engineering : complete field survey for Francis & Stearns roads for proposed 3 phase service to site on 6/10/24.
Larson waterproofing: completed phase #2 exterior foundation walls.

Pittol concrete: continue top of wall embeds, should complete 6/11/24.
Conneely excavating : back fill phase #2 foundation wall up 5’-0” / install perimeter drain phase #2 / start excavating for underground plumbing 6/11/24
White cap : deliver wire mesh ,chairs ,slab dowels for SOG 6/12/24
 Joyce Plumbing : to deliver materials for underground plumbing 6/14/24

6/17/24 :

Conneely finish prepping underground excavation at west end/phase #2 w/ sand, prep areas for retaining walls/north,storm system, backfill underground phase 2 after inspection/prep phase #2 for slab ( 3/4 stone)
Joyco Plumbing : start underground plumbing, test phase 2, finish phase #1 & test

6/24/24 : Plumbing - complete under ground, trap primers, set floor drains to proper elevations prep drains for concrete pour
Conneely excavating : prep phase #1 for slab ( 3/4 stone )
Pittol concrete: prep phase #1 & #2 pour stops, slab dowels, expansion joint filler, 6 mill. poly, wire mesh, pour/broom finish phase #1 SOG.