3 week look ahead 6/24

Week of 6/24/24 : Plumbing performing underground plumbing

Week of 7/1/24 : Plumbing per coordination with Tim will finish underground plumbing and test on 7/1/24 and have Wellesley plumbing inspector inspect on 7/2/24
Start backfilling, prep for SOG , to have complete by 7/5/24
Start and complete slab prep by 7/5/24

Week of 7/8/24 : Place and finish pour #1 & #2 SOG, cure & seal concrete. Form & pour exterior sono tube & footings for deck supports .
Prep areas for anticipated steel delivery on week of 7/15/24