3 Week look ahead
Week of 5 /13/24 : Layout for phase #2 walls
Foundations- tie / form walls / set leveling plates @ interior columns / install beam pockets & top of wall shelf .
Inspect re-bar phase #2 walls
Build south cmu stairwell walls
Prep exterior deck footings
Week of 5/20/24 : Pour phase #2 walls & exterior deck footings / strip walls & exterior deck footings/ de-mobe
Start prep for plumbing underground / start north precast concrete retaining wall
Damproof /drainage board /insulate phase #2 walls.
As built phase #2 foundation
Start underground plumbing
Week of 5/27/24 : Underground plumbing prep/ perimeter drain phase #2 /precast concrete retaining wall / backfill foundation phase #2 / prep slab on grade
Form column diamond box outs / install 2” rigid insulation at perimeter/ install 6 mill. Poly vapor barrier & 6”x6”x2.9 mil wwf mesh / premoulded filler ( expansion material) / form / box out 1st phase sog pour . Install tow embeds phase #1 
Week of 6/3/24 : Pour phase #1 & #2 SOG
Prep site for this week scheduled steel delivery
Deliver steel / start erecting