3 week look ahead 7/8

Week of 7/8/24:

Plumbing continues underground plumbing, underground plumbing inspection scheduled for 7/9/24 between 11 & 1 pm. Start backfilling underground post inspection on 7/10/24 along with plumbing.

Week of 7/15/24 : Back filling underground and slab prep (3/4” stone pre or post steel)


Week of 7/22/24 : Deliver crane and sequence #1 steel, start erecting, sequence #2 & #3 and decking to follow over following couple of weeks appropriately