3 WEEK LOOK AHEAD 3/3
Week of 3/3/25:
Exterior siding/ trim - currently at approximately 50%
Sprinkler - level #1 rough , sidewall heads at exterior decks
Electrical- level #1 rough ongoing
HVAC - level #1 rough ongoing , linesets scheduled to be on site wed .
Plumbing - level #2 water piping . Level #1 pvc ongoing ,layout for cores
Week of 3/10/25 :
JP Sales - siding continue
Sprinkler -level #1 rough ongoing ,level #3 wet rough ongoing
Electrical - level #1 rough ongoing
HVAC - level #1 rough ongoing ,linesets ongoing
Plumbing - level #1 pvc rough ongoing ,lay out for SOD Cores , vent pvc through roof
Week of 03/17/25 :
Siding ongoing
Sprinkler - level #1 rough ongoing ,level #3 wet rough ongoing
Electric - level #1 rough ongoing
HVAC - level #1 rough ongoing ,linesets & RTU install
Plumbing- level # pvc rough,water piping ,pvc vents through roof ongoing , set tubs & Showers - tubs,pans , valves level #2 & #1
-level #1 rough ongoing