3 week look ahead 3/24
Week of 3/17/25:
Siding - Siding/trim of west and front elevations
Sprinkler - Level 1 rough ongoing, take delivery of 3rd level black iron mains/start attic rough mains
Electrical - Level 1 roughs, cut in panels on level 1 and 3
HVAC - Level 1 roughs, line sets to the roof
Plumbing - Level 1 water piping, receive 1st shipment of tubs, install tubs and shower valves level 1 and 2, vents through the roof
Roofing - Shingle front porch roofs
Week of 3/24/25:
Frame level 1 decks units 106 and 107, punch list on decks south elevation, clean up yard
Steel - Install added beams
Siding on going
Sprinkler - install dry system level 3 attic mains
Electrical - line sets to the roof, level 1 roughs, start switchgear
HVAC - line sets to the roof, level 1 and 2 roughs clean up punch
Plumbing - Level 1 pvc rough on going, water piping, tub sets and valves at level 2 ongoing, roof vents, and shower pan drains
Verizon - Install micro duct for all units
Week of 3/31/25:
Siding on going
Roof boots/pitch pockets/candy canes
Sprinkler - Level 3 attic dry system and wet roughs
Electrical - Level 1 rough ongoing, switch gear ongoing, rough EMR
HVAC - Line sets, RTUs, level 1 rough ongoing/rough EMR
Plumbing - Set tubs and valves on 1 and 2, shower drains, and valves on 1 and 2, and roof vents
Rough inspections electrical, plumb, sprinkler, hvac and insulation week of 3/31/25 level 2