3 Week look ahead 2/3
Week of 2/3/25:
Siding - exterior prep for siding and trim ongoing
Sprinkler - level #2 & #1 ongoing
Electrical - level#2 & #1 roughs ongoing
HVAC - level #2 & #1 roughs ongoing
Plumbing - level #2 & #1 pvc rough ongoing
Frame - porches ,decks ,stairs ongoingWeek of 2/10/25:
Siding - installing pvc trim , sub fascia front porches ,fire tape electrical and sprinkler rooms & hang fire treated plywood
Sprinkler : level #2 & #1 roughs ongoing
Electrical- level #1 rough ongoing
HVAC- level #1 rough ongoing
Plumbing -level #2 & #1 pvc rough ongoing
Week of 2/17/25:Siding: exterior pvc trim
Sprinkler level #1 rough ongoing
Electrical level #1 rough ongoing
HVAC - level #1 rough ongoing
Plumbing - level #1 pvc rough ongoing