3 week look ahead 1/6
Week of 1/6/25 :
Exterior trim - water table ,exterior 1” rigid insulation,window / door installation complete .
Complete south stair rough , garage door & louvre openings blocking , fire treated backing / blocking for electrical room.
Waterproofing co. : complete foundation waterproofing south and west elevations .
Electrical : complete panel feeds , start roughs ,start electrical switch gear in electrical room ,install tel/ data unit boxes
Sprinkler : start south stair riser , FDC to front entry
Drywall : pre rock continues , fire tape post heat
Green Insulation : insulate pre rock
Frame south decks ,front porches, clean up , punch
HVAC : start roughs - line sets to roof tops & units
Plumbing : start roughs - level 3 ,2,1
Site: scheduled to excavate tel/ data trench / #3 light pole bases
Week 1/13/25 :
Continue exterior trim , make ready for siding
Build temp doors to close in for heat ,siding ,trim,
Decking balconies, tapered columns
Electrical : switch gear , unit roughs level #3
Sprinkler : south standpipe level #3 roughs
Drywall : level #2  prerock /frame garage partitions for electrical,sprinkler, elevator machine room , trash rooms , one side Sheetrock
Insulation: pre rock insul.
Frame: porches ,decks , punch
HVAC : level#3 roughs , roof top units
Plumbing : level #3 roughs
Week of 1/21/25 :
Decks , rails ,siding
Electrical:switch gear , level #3 rough
Sprinkler : level #3 rough
Drywall - level #1 pre rock
Insulation: pre rock insulation
Frame decks ,porches ,punch
HVAC : level #2 roughs
Plumbing : level #2 rough