3 week look ahead 10/14
Week of 10/14/24 :
Complete spray fireproofing on 10/15/24
Frame : punch level 1 & 2, complete level #3 walls, deliver roof trusses Monday & start installing.
#2 laborers trench stone at garage level for electrical conduits for charging stations & garage door operator. Trench for radon vent 4” perforated schedule 40. Cut/demo safety rail stands #50 pcs level #1
Electrical : install under slab conduit for charging stations, garage door operator, conduit for transformer pad, temp pole service w/ temp service panel, temp lights level #1 & #2
Concrete: prep for garage slab post underground electrical inspection - expansion joint premoulded filler, 6 mil. Poly, wire mesh, slab dowels, pour stops
Plumbing : possible MWRA tank inspection this week, complete piping vents and drain in and out of tank, install radon pipe ( co)
Site: possible backfill oil, gas, water separator tank, set temp service pole for electrical, install remaining catch basin SW corner of site, install sanitary to existing SMH, possible install water service out of street pending application approval with town of Wellesley water dept., set transformer pad with electrical
Foundation Waterproofing: possible install south & west elevations AVB/waterproofing on exposed concrete above finish grade to level #1 floor .
Week of 10/21/24 :
Frame: Installing roof trusses, window blocking per pending detail from architect , finish punch level #2 & & #3 , roof decking ,start building stairs pending requested stair details from architect
Concrete: continue prep for slab pour #1, place and finish pour #1 garage, prep for garage pour #2, form and pour front porch pier footings
Site : excavate for front porch pier footings, water service, electrical & tel/ data service
Plumbing : layout for cores level #1 , penetrations for levels #2 & #3 at floors .
Electrical: layout recessed light locations levels #1,#2 & #3
Fire protection: layout sprinkler head locations @ levels #1, #2 & #3 on floors & exterior wall penetrations, possible start stand pipes at stairwells post stair framing .
HVAC contractor : layout for exterior wall penetrations, floor penetrations at levels #1, #2 & #3 & equipment roof & roof deck blocking post roof decking. Layout for ceiling diffusers at levels #1 ,#2 
Week of 10/28/24 :
Frame: complete roof trusses and roof decking, install windows, leave flashing detail for siding contractor, build decks, trim rakes & soffits, build front porches & decks & rails, finish building stairs & landings
Plumbing: roughs ongoing starting at level #2,core level #1 SOD holes post SOG pour #2 .
Fire Protection : install ongoing starting at level #1 ceilings & stairwells standpipes
Concrete : garage SOG pour #2
Roofing Contractor : install roof
Siding Contractor : installing Blue skin AVB post window install
All MEP’s install penetrations at envelope & roof